Crystal River Airport Runway 9/27 Extension
Summary
The main runway extension project is still in environmental assessment, now with a new completion date of October 19. FAA review times have stretched from 60 to 120 days, pushing the schedule.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 12, 2026.
Impact analysis
Grant timelines affect whether the county must cover costs if deadlines slip.
Pilots and businesses that will gain a longer, more capable runway at Crystal River.
Mentions & discussions (4)
Aviation Advisory Board - Nov 12, 2026
The environmental assessment for extending the runway is 95% done and awaiting an FAA decision, which would improve safety and aircraft performance. But a NOTAM restricting approach minimums is still in effect despite expectations it would be cleared.
Aviation Advisory Board - Jul 9, 2026
The Crystal River runway extension is in its environmental assessment phase, and the board pressed on whether grant deadlines could be met. Staff said extensions have routinely been granted.
Aviation Advisory Board - Jun 11, 2026
The FAA has cleared the project to move into its public workshop phase, with a meeting expected July 16. The project remains within budget, and staff is pursuing a wetland mitigation grant.
Aviation Advisory Board - Feb 12, 2026
The main runway extension project is still in environmental assessment, now with a new completion date of October 19. FAA review times have stretched from 60 to 120 days, pushing the schedule.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Citrus County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.