Forest Lake North residents say a concrete plant's pre-dawn noise, vibration, backup alarms and lighting are disrupting sleep and health, and they can't find a clear path forward after code enforcement closed the case. Staff promised an internal meeting on legal and ordinance options and a report back at the next meeting.
At a glance
- Total mentions
- 12
- Last 30 days
- 5
Rising — discussed at 3 meetings since Sep 21, 2026, up from 1 in the two months before.
Impact analysis
No direct county cost, but a failed attempt to reverse the zoning could trigger taxpayer-funded legal liability.
Residents near the plant if the county finds an enforcement or nuisance remedy.
Nearby households report lost sleep, health effects and reduced enjoyment of their homes.
Mentions & discussions (8)
Board of County Commissioners Regular Meeting - Nov 17, 2026
Forest Lake North residents say a concrete plant's pre-dawn noise, vibration, backup alarms and lighting are disrupting sleep and health, and they can't find a clear path forward after code enforcement closed the case. Staff promised an internal meeting on legal and ordinance options and a report back at the next meeting.
Board of County Commissioners - Oct 26, 2026
Hernando residents say a cement plant's pre-7 a.m. noise continues despite a resident-plant-code enforcement meeting that ended without resolution; the code case was closed. Speakers urged separating code enforcement from the growth management department and extending data-center-style rules to all industrial uses.
Board of County Commissioners Regular Meeting - Sep 21, 2026
Hernando residents again demanded action on around-the-clock noise from a cement facility near homes; the board agreed to have staff draft decibel/hours standards and route them through the PDC.
Board of County Commissioners Regular Meeting - Aug 11, 2026
Forest Lakes North residents played recordings of daily industrial noise from the cement plant and asked the board for enforcement, buffering review, and permitting transparency. Commissioners asked staff to examine code time limits for industrial operations.
Board of County Commissioners Regular Meeting - Jul 14, 2026
Neighbors say the heavy industrial concrete plant near homes and the Withlacoochee State Trail produces noise up to 93 decibels at 3 a.m., hurting sleep, health, and property values. Code enforcement says the plant is in compliance; residents want a compatibility review.
Board of County Commissioners Regular Meeting - Jun 11, 2026
Neighbors say a reopened cement plant near the Withlacoochee State Trail runs loud from early morning with dust and runoff; they want a formal compatibility review.
Planning and Development Commission - May 21, 2026
The LDC update would force cement batch plants in light industrial — and both cement and asphalt plants in heavy industrial — through a PUD review instead of by-right or simple conditional use approval. Residents living near an existing plant described round-the-clock noise.
Board of County Commissioners Regular Meeting - Jan 6, 2026
Residents learned a concrete plant is coming within 500 feet of homes near the Withlacoochee Trail. The land has been industrially zoned since about 1990, so the county says it legally cannot block it — but promises enforcement of noise, dust and hours rules.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Citrus County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.