Permanent Equalization Tank and Wastewater Capacity
Summary
The city is replacing its leased temporary tank with a permanent 3-million-gallon-per-day equalization tank near the wastewater plant, about half grant-funded. It manages high wet-season flows — key to the Waterkeepers litigation consent order compliance.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 26, 2026.
Impact analysis
An $88,766 unpaid invoice was paid via emergency procurement; the permanent tank is roughly half covered by grants.
Residents get better wastewater capacity and reduced overflow risk during heavy rains.